01/08/2006


Biomass Filter Aberthaw Power Station


Project Status

Previous Project


Project Outline

The design, installation, testing of the\\r\\nelectrical and instrumentation cabling and\\r\\ncontainment for a new Biomass Filter at\\r\\nAberthaw Power Station


Description

Electrical, Instrumentation and Building Services installation and testing.


Full Description

Design, procurement, installation and testing of cables, containment services for new Biomass Filter Scheme


Contract Duration

16 weeks


Contract Value

£300,000


Additional Contract Details

Subcontract to Mowlem Power


Services Provided

Electrical, Instrumentation and Building Services


Main Contractor

Mowlem Engineering


End User

nPower


Consultants

Mowlem Engineering


Completion Date

01/11/2006


Division

Process


Biomass Filter Aberthaw Power Station