01/10/2007


South Humber Bank Power Station


Project Status

Previous Project


Project Outline

Testing and remedial work associated with the Building Services


Description

Electrical, Instrumentation and Building Services installation testing and remedial work.


Full Description

Design, procurement, installation and testing of cables, containment and building services


Contract Duration

20 weeks


Contract Value

£75,000


Additional Contract Details

Subcontract to Centrica


Services Provided

Electrical, Instrumentation and Building Services


Main Contractor

Centrica


End User

Centrica


Consultants


Completion Date

01/02/2008


Division

Process


South Humber Bank Power Station